Construction Weekly Project Update 5/01/2017
- Bridges
- Retaining Walls
- I-84
- Local Roads
- Night Work
- Rock Blasting
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Excavate abutment 1 footing
- Blast and excavate pier 1 footing
- Form and rebar pier 1 footing
Bridge 6590 (EB 25 on ramp)
- Drill and blast abutment 1 area
- Install drainage structures and pipes
Bridge 1224 (I-84 bridge over Mad River, western crossing)
- Form and pour abutment 1 backwalls
- Form and pour abutment 2 stem
Bridge 1226 (Harpers Ferry Road Bridge)
- Set structural steel
- Install utility hangers/conduits/gas
Bridge 5774 (future I-84 bridge over Mad River)
- Rebar WB deck
- Set Gomaco deck machine and test run EB deck
- Pour concrete for EB deck
Bridge 6284 (future EB 25 off ramp)
Retaining Walls
Retaining Wall 101 (along WB I-84 and east of WB 23 off ramp)
Retaining Wall 106 (north of WB I-84 west of WB 25 off ramp)
- Continue soil nail and excavation
I-84
- EB: Rock blasting for new EB 25 off ramp from Hamilton Ave. to Bridge 1224
- EB: Rock blasting east of EB 23 on ramp to Austin Road
- WB: Install sound barrier wall along new WB 25 off ramp
Local Roads
Reidville Drive
- Grade drainage swale on ridge and slopes
- Form and pour cut-off and culvert pours for Culvert 003 (east of rock cut; under Reidville Drive)
Plank Road (Cul-de-sac to Harpers Ferry Road)
- Cut and fill roadway section
- Set curb and subbase
Farrell Road
- Continue to excavate and place subbase material
Plank Road East
- Culvert 06622 (West of Scott Road) Set modular wingwall
- Culvert 02537 (Beaver Pond Brook under I-84, south of WB 25 on ramp) water work
Night Work
- Miscellaneous pothole repair and drainage
Rock Blasting
Rock blasting to occur:
- West end of project - between Hamilton Avenue Bridge and Bridge 1224
- East end of project - east of EB 23 on ramp to Austin Road
When I-84 needs to be stopped for safety reasons, blasting will occur on Tuesday, Wednesday, and Thursday between 9:30 AM and 11:30 AM. When no traffic stoppage on I-84 is required blasting may occur Monday through Friday from 9:00am – 3:00pm.
Traffic stoppages on local roads including Hamilton Avenue, Scott Road and Reidville Drive to be implemented at time of blasts for safety reasons.
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.