I-84 Waterbury Widening

I-84 Waterbury Widening

Images go here.

Construction Weekly Project Update 4/24/2017

Bridges

Bridge 4321 (Hamilton Avenue over I-84)

Bridge 6590 (EB 25 on ramp)

Bridge 1224 (I-84 bridge over Mad River, western crossing)

Bridge 1226 (Harpers Ferry Road Bridge)

Bridge 5774 (future I-84 bridge over Mad River)

Retaining Walls

Retaining Wall 101 (along WB I-84 and east of WB 23 off ramp)

Retaining Wall 106 (north of WB I-84 west of WB 25 off ramp)

I-84 EB

I-84 WB

Local Roads

Reidville Drive

Harpers Ferry Road/Plank Road

Farrell Road

Plank Road East

Night Work

Rock Blasting

Rock blasting to occur between Hamilton Avenue Bridge and Bridge 1224.
When I-84 needs to be stopped for safety reasons, blasting will occur on Tuesday, Wednesday, and Thursday between 9:30 AM and 11:30 AM. When no traffic stoppage on I-84 is required blasting may occur Monday through Friday from 9:00am – 3:00pm.
Traffic stoppages on Hamilton Avenue to be implemented at time of blasts for safety reasons.

Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)

Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.