Construction Weekly Project Update 4/24/2017
- Bridges
- Retaining Walls
- I-84
- Local Roads
- Night Work
- Rock Blasting
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Excavate and install support of excavation abutment 1
- Excavate pier footing
Bridge 6590 (EB 25 on ramp)
- Drill and blast abutment 1 area
Bridge 1224 (I-84 bridge over Mad River, western crossing)
- Backfill abutment 1 to top of stem and remove cofferdam
- Form and pour abutment 1 backwalls
- Form and pour abutment 2 stem
Bridge 1226 (Harpers Ferry Road Bridge)
Bridge 5774 (future I-84 bridge over Mad River)
- Form EB & WB deck
- Rebar EB & WB deck
Retaining Walls
Retaining Wall 101 (along WB I-84 and east of WB 23 off ramp)
- Excavate footing
- Form and pour leveling pad
Retaining Wall 106 (north of WB I-84 west of WB 25 off ramp)
- Continue soil nail and excavation
I-84 EB
- Rock blasting for new EB 25 off ramp from Hamilton Ave. to Bridge 1224
- Pave EB 25 off ramp (from Bridge 1224 to Bridge 6284) Night work
I-84 WB
- Install sound barrier wall along new WB 25 off ramp
- Pave new WB 25 off ramp – Night work
Local Roads
Reidville Drive
- Install drainage (Reidville Drive and Harpers Ferry Road)
- Place subbase and fine grade (Future Reidville Drive area)
- Form and pour cut-off and culvert pours for Culvert 003 (east of rock cut; under Reidville Drive)
- Form and pour cut-off and wingwall for Culvert 1227 (east of the rock cut; under future I-84)
Harpers Ferry Road/Plank Road
- Pipework – Install drainage
Farrell Road
- Continue to excavate and place subbase material
Plank Road East
- Pave – Night work
- Culvert 06622 (West of Scott Road) Set modular wingwall
- Culvert 02537 (Beaver Pond Brook under I-84, south of WB 25 on ramp) Construct wingwalls
Night Work
- Paving – WB 25 off ramp, Plank Road East, and EB 25 off ramp
- Miscellaneous pothole repair and drainage
Rock Blasting
Rock blasting to occur between Hamilton Avenue Bridge and Bridge 1224.
When I-84 needs to be stopped for safety reasons, blasting will occur on Tuesday, Wednesday, and Thursday between 9:30 AM and 11:30 AM. When no traffic stoppage on I-84 is required blasting may occur Monday through Friday from 9:00am – 3:00pm.
Traffic stoppages on Hamilton Avenue to be implemented at time of blasts for safety reasons.
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.