Construction Weekly Project Update 3/27/2017
- Bridges
- Retaining Walls
- I-84
- Local Roads
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Demolish abutment 1 (night work)
- Excavate and install support of excavation abutment 1
- Excavate pier 1 footing
Bridge 6590 (EB 25 on ramp)
- Pour wingwalls abutment 2 stem walls
Bridge 1224 (I-84 bridge over Mad River, western crossing)
- Form and pour stem abutment 1
- Drive cofferdam and piles, abutment 2
Bridge 1226 (Harpers Ferry Road Bridge)
- Steel delivery scheduled for Tuesday 10:00 AM – 3:00 PM
- Erect structural steel
Bridge 5774 (future I-84 bridge over Mad River)
Bridge 6284 (future EB 25 off ramp over Mad River)
- Place subbase material for ramp from Bridge 1224 to Bridge 6284
Bridge 1228 (Scott Road Bridge)
- Form and pour center pier column
Retaining Walls
Retaining Wall 106 (north of WB I-84 west of WB 25 off ramp)
- Continue soil nail and excavation
Retaining Wall 109 (along I-84, east of WB Exit 25 off ramp)
I-84
- WB: Install sound barrier wall along Retaining Wall 109, west of Pierpont Road
- WB: Place subbase material new WB 25 off ramp
Local Roads
Reidville Drive
- Install drainage at rock cut
- Form and pour footing for Culvert 003 (east of rock cut; under Reidville Drive)
- Set Culvert 003
- Form and pour footing for Culvert 1227 (east of the rock cut; under future I-84)
Harpers Ferry Road/Plank Road
- Pipework – Install drainage
Farrell Road
- Excavate and place subbase material
Night Work
- I-84 barrier relocation
- Abutment 1 demolition at Hamilton Avenue Bridge
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.