Construction Weekly Project Update 3/13/2017
- Bridges
- Retaining Walls
- I-84
- Local Roads
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Excavate and demolish abutment 2 (night work)
- Excavate and install support of excavation abutment 1
Bridge 1224 (I-84 bridge over Mad River, western crossing)
- Form and pour footing and stem abutment 1
- Mobilize Drive cofferdam and piles, abutment 2
Bridge 1226 (Harpers Ferry Road Bridge)
- Backfill abutment 2
- Erect structural steel
- Set bearings
Bridge 5774 (future I-84 bridge over Mad River)
- Install stay in place forms for bridge deck
- Form bulkhead and fascia brackets
Bridge 1228 (Scott Road Bridge)
- Form and pour center pier column
Retaining Walls
Retaining Wall 106 (north of WB I-84 west of WB 25 off ramp)
I-84
- WB: Install sound barrier wall along Retaining Wall 109, west of Pierpont Road
- WB: Fill new WB 25 off ramp
Local Roads
Reidville Drive (Culvert 003 vicinity at eastern end of rock cut)
- Excavate and install support of excavation
Harpers Ferry Road/Plank Road
Night Work
- I-84 barrier relocation
- Demolish abutment 2 at Hamilton Avenue Bridge (night work)
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.