Construction Weekly Project Update 2/20/2017
- Bridges
- Retaining Walls
- I-84
- Local Roads
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Demolish abutments of eastern portion of bridge
Bridge 6590 (EB 23 on ramp from Hamilton Avenue)
- Form and pour abutment 2 stem walls
Bridge 1224 (I-84 bridge over Mad River, western crossing)
- Drive piles for abutment 1
- Form and pour footing abutment 1
- Install sound barrier wall along south side of EB 25 off ramp
Bridge 1226 (Harpers Ferry Road Bridge)
- Form and pour abutment 2 pedestals and back wall
- Prep for steel delivery – scheduled for Tuesday – Thursday 10:00 AM – 3:00 PM
- Pre-assemble structural steel
Bridge 5774 (future I-84 bridge over Mad River)
- Install stay in place forms for bridge deck
Bridge 1228 (Scott Road Bridge)
- Form and pour center pier footing
Retaining Walls
Retaining Wall 106 (north of WB I-84 west of WB 25 off ramp)
I-84
- EB: Install sound barrier wall between Retaining Wall 104 and Bridge 1224
- WB: Fill new WB 25 off ramp
Local Roads
Scott Road/Plank Road East
- Pipework – Install drainage structures
Harpers Ferry Road/Plank Road
- Pipework – Install water main service connections
Night Work
- I-84 barrier relocation
- Temporary line striping (project wide)
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.