Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Demolish abutments of eastern portion of bridge
Bridge 6590 (EB 23 on ramp from Hamilton Avenue)
- Form and pour abutment 2 stem walls
Bridge 1224 (I-84 bridge over Mad River, western crossing)
- Drive piles for abutment 1
- Form and pour footing abutment 1
- Install sound barrier wall along south side of EB 25 off ramp
Bridge 1226 (Harpers Ferry Road Bridge)
- Form and pour abutment 2 stemwall, wingwall and back wall
- Prep for steel delivery – scheduled for Tuesday – Thursday 10:00 AM – 3:00 PM
Bridge 6284 (future EB 25 off ramp over Mad River)
- Form and pour bridge counterweights
Bridge 1228 (Scott Road Bridge)
- Form and pour abutment 1 wingwall footing
- Excavate and install support of excavation for center pier footing
- Place granular fill at pier
Retaining Walls
Retaining Wall 106 (north of WB I-84 west of WB 25 off ramp)
I-84
- EB: Install sound barrier wall between Retaining Wall 104 and Bridge 1224
- WB: Fill new WB 25 off ramp
Local Roads
Reidville Drive (Culvert 003 vicinity at eastern end of rock cut)
- Excavate and install support of excavation
Plank Road East (Culvert 6622, west of Scott Road)
- Excavate and install leveling pads for wingwall closure wall with Retaining Wall 108, west of the culvert
- Set modular wingwall
Scott Road/Plank Road East
- Pipework – install drainage structures
East Main Street/Scott Road
- Drill test pits for utilities – Night work
Harpers Ferry Road/Plank Road
- Install water main service connections
Night Work
- I-84 barrier relocation
- East Main Street/Scott Road – Drill test pits for utilities
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.