Construction Weekly Project Update 2/06/2017
- Bridges
- Retaining Walls
- I-84
- Local Roads
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Remove old girders (eastern portion) – Night work
Bridge 6590 (EB 23 on ramp from Hamilton Avenue)
- Form and pour abutment 2 stem walls
Bridge 1224 (I-84 bridge over Mad River, western crossing)
- Drive piles for abutment 1
- Form and pour footing abutment 1
- Install sound barrier wall along south side of EB 25 off ramp
Bridge 5774 (future I-84 over Mad River, eastern crossing)
Bridge 6284 (future EB 25 off ramp over Mad River)
- Form and pour bridge counterweights
Bridge 1228 (Scott Road Bridge)
- Form and pour abutment 1 wingwall footing
- Form and pour abutment 2 wingwall footing
- Excavate and install support of excavation for center pier footing
- Place granular fill at pier
Retaining Walls
Retaining Wall 106 (north of WB I-84 west of WB 25 off ramp)
I-84
- EB: Install sound barrier wall between Retaining Wall 104 and Bridge 1224
- WB: Fill new WB 25 off ramp
Local Roads
Reidville Drive (Culvert 003 vicinity at eastern end of rock cut)
- Excavate and install support of excavation
Plank Road East (Culvert 6622, west of Scott Road)
- Excavate and install leveling pads for wingwall closure wall with Retaining Wall 108, west of the culvert
Scott Road/Plank Road East
- Pipework – install drainage structures
East Main Street/Scott Road
- Drill test pits for utilities – Night work
Harpers Ferry Road/Plank Road
- Install 18” water main tie-in (night work), followed by water main service connections (daytime work)
Night Work
- Hamilton Avenue Bridge – Demolition
- East Main Street/Scott Road – Drill test pits for utilities
- Plank Road – Water main tie-in
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.