Construction Weekly Project Update 1/30/2017
- Bridges
- Retaining Walls
- I-84
- Local Roads
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Demolish existing superstructure (eastern portion)
Bridge 6590 (EB 23 on ramp from Hamilton Avenue)
- Excavate center pier footing
- Form and pour abutment 2 stem walls
- Install drainage structures
Bridge 1224 (I-84 bridge over Mad River, western crossing)
- Drive cofferdam and piles for abutment 1
- Install sound barrier wall along south side of EB 25 off ramp
Bridge 5774 (future I-84 over Mad River, eastern crossing)
- Deliver girders to project Tuesday through Wednesday 10:00 AM – 3:00 PM
- Set structural steel
Bridge 6284 (future EB 25 off ramp over Mad River)
- Form and pour bridge counterweights
Bridge 1226 (Harpers Ferry Road over I-84)
- Form and pour stem wall abutment 2
- Form and pour wingwall stems
Retaining Walls
Retaining Wall 106 (north of WB I-84 west of WB 25 off ramp)
Retaining Wall 109 (along I-84, east of WB Exit 25 off ramp)
- Set and backfill modular blocks
I-84
- EB: Install sound barrier wall between Retaining Wall 104 and Bridge 1224
- WB: Fill new WB 25 off ramp
Local Roads
Reidville Drive (Culvert 003 vicinity at eastern end of rock cut)
- Excavate and install support of excavation
Plank Road East (Culvert 6622, west of Scott Road)
- Set modular wingwall (closure wall with Retaining Wall 108, west of the culvert)
Scott Road/Plank Road East
- Pipework – install drainage structures
Night Work
No night work this week.
Waste Stockpile Area (WSA)/Reuse Stockpile Area (RSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to RSA at Exit 30 WB.