Construction Weekly Project Update 1/23/2017
- Bridges
- Retaining Walls
- I-84
- Culverts and Utility Work – Local Roads
- Rock Blasting
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Demolish existing superstructure (eastern portion) – night work
Bridge 6590 (EB 23 on ramp from Hamilton Avenue)
- Install drainage structures
Bridge 1224 (I-84 bridge over Mad River, western crossing)
- Drive cofferdam and piles for abutment 1
Bridge 5774 (future I-84 over Mad River, eastern crossing)
- Deliver girders to project Tuesday through Thursday 10:00 AM – 3:00 PM
- Set structural steel
Bridge 6284 (future EB 25 off ramp over Mad River)
- Form and pour bridge counterweights
Bridge 1226 (Harpers Ferry Road over I-84)
- Form and pour stem wall abutment 2
Retaining Walls
Retaining Wall 106 (north of WB I-84 west of WB 25 off ramp)
Retaining Wall 109 (along I-84, east of WB Exit 25 off ramp)
- Form and pour leveling pad
I-84
- EB: Drill foundations for sound barrier wall between Retaining Wall 104 and Bridge 1224
- WB: Fill new WB 25 off ramp
Culverts – Local Roads
Reidville Drive (Culvert 003 vicinity at eastern end of rock cut)
- Excavate and install support of excavation
Plank Road East (Culvert 6622, west of Scott Road)
- Excavate and install leveling pads for wingwall closure wall with Retaining Wall 108, west of the culvert
Scott Road (Culvert 014 at Scott Road south of WB 25 off ramp)
Utility Work – Local Roads
East Main Street/Scott Road
- Excavate utility test pits – night work
Night Work
- Hamilton Avenue Bridge demolition
- East Main Street/Plank Road – excavate utility test pits
Waste Stockpile Area (WSA)/Reuse Stockpile Area (RSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to RSA at Exit 30 WB.