Construction Weekly Project Update 11/28/2016
- Bridges
- Retaining Walls
- I-84
- Local Roads
- Rock Blasting
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Demolish existing superstructure (eastern portion)
Bridge 1224 (I-84 bridge over Mad River, western crossing)
- Install cofferdam; demolish center pier
Bridge 5774 (future I-84 over Mad River, eastern crossing)
- Form and pour back walls abutment 2
Bridge 1226 (Harpers Ferry Road over I-84)
- Form and pour back wall abutment 1
- Form and pour footing abutment 2
Bridge 1228 (Scott Road Bridge over I-84)
- Form and pour wing wall footings at abutment 1 (south side of I-84)
- Form and pour wing wall stems at abutment 2 (north of I-84)
Retaining Walls
Retaining Wall 116 (adjacent to Harpers Ferry Road bypass vicinity)
- Excavate and pour leveling pad
Retaining Wall 106 (north of WB I-84 west of WB 25 off ramp)
- Prep for soil nailing
- Soil nail and excavation
Retaining Wall 113 and 114 (along both sides of future EB 25 off ramp)
- Install parapet moment slab 114
Local Roads
Harpers Ferry Road/Plank Road
- Install 18” water main and services
Reidville Drive
- Excavate and install support of excavation at Culvert 003 (just east of the rock cut)
- Install utility trench
- Excavation & trucking of materials
- One lane closed intermittently with alternating traffic
Scott Road (Culvert 014 at Scott Road south of WB 25 off ramp)
- Form and pour southern wing wall leveling pad
Plank Road East (Culvert 02537 at Beaver Pond Brook under WB I-84, east of WB 25 on ramp)
- Form and pour cutoff footing between Retaining Wall 108 – along I-84, east of WB 25 on ramp – and culvert
- Beaver Pond Brook channel excavation
Rock Blasting
- No rock blasting is anticipated this week.
Night Work
- Barrier placement and drainage
Waste Stockpile Area (WSA)/Reuse Stockpile Area (RSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to RSA at Exit 30 WB.