Construction Weekly Project Update 11/21/2016
- Bridges
- Retaining Walls
- I-84
- Local Roads
- Rock Blasting
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Demolish existing superstructure (eastern portion)
Bridge 1224 (I-84 bridge over Mad River, western crossing)
Bridge 5774 (future I-84 over Mad River, eastern crossing)
- Form and pour back walls abutment 2
Bridge 1226 (Harpers Ferry Road over I-84)
- Form and pour back wall abutment 1
- Form and pour footing abutment 2
Bridge 1228 (Scott Road Bridge over I-84)
- Form and pour wing wall footings at abutment 1 (south side of I-84)
- Form and pour wing wall stems at abutment 2 (north of I-84)
Retaining Walls
Retaining Wall 106 (north of WB I-84 west of WB 25 off ramp)
- Excavate and grade slope
- Prep for soil nailing
Retaining Wall 113 and 114 (along both sides of future EB 25 off ramp)
- Install parapet moment slab 114
I-84
I-84 WB (from Exit 25A off ramp to Exit 25 off ramp vicinity)
I-84 WB 23 off ramp
- The existing WB 23 off ramp is closed and WB Exit 23-bound traffic has been detoured to WB Exit 22 for a 48-hour period. The new off ramp will open Saturday, November 19 (If weather issues occur, the opening will be delayed until Sunday, November 20).
I-84 EB (Between EB 23 on ramp and Bridge 1224)
Drill foundation for noise wall
Local Roads
Harpers Ferry Road/Plank Road
- Install 18” water main and services
Reidville Drive
- Install utility trench
- Excavation & trucking of materials
- One lane closed intermittently with alternating traffic
Scott Road (Culvert 014 at Scott Road south of WB 25 off ramp)
Plank Road East
- Beaver Pond Brook channel excavation
Rock Blasting
- No rock blasting is anticipated this week.
Night Work
- Lighting along I-84 median
- WB 23 off ramp
Waste Stockpile Area (WSA)/Reuse Stockpile Area (RSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to RSA at Exit 30 WB.