I-84 Waterbury Widening

I-84 Waterbury Widening

Images go here.

Construction Weekly Project Update 10/31/2016

Bridges
Bridge 4321 (Hamilton Avenue over I-84)
Form and rebar parapet and sidewalk
Install protective shielding

Bridge 1224 (I-84 bridge over Mad River, western crossing)
Continue demolition of northern portion of bridge and excavate
Install approach slab EB 25 off ramp
Install parapet EB 25 off ramp

Bridge 5774 (future I-84 over Mad River, eastern crossing)
Form and pour stem walls

Bridge 6284 (future EB 25 off ramp over Mad River)
Set structural steel and bolt up

Bridge 1226 (Harpers Ferry Road over I-84)
Strip forms, apply damp-proofing, and backfill

Bridge 1228 (Scott Road Bridge over I-84)
Form and pour stem walls at abutment 2 (north of I-84)
Form and pour stem walls at abutment 1 (south side of I-84)

Retaining Walls
Retaining Wall 108 (along I-84, east of WB 25 on ramp)
Set parapet sections

Retaining Wall 113 and 114 (along both sides of future EB 25 off ramp)
Install parapet moment slab 113 & 114

Retaining Wall 116 (adjacent to Harpers Ferry Road bypass)
Excavate and pour leveling pad

I-84
Median reconstruction from Pierpont Road to WB 25 off ramp
Complete guide barriers
Backfill conduit and light pole foundations
Pour concrete cap

I-84 EB (Between EB 23 on ramp and Bridge 1224)
Drill foundation for noise wall

EB 23 on ramp
Prep for construction of temporary ramp

Local Roads
Hamilton Avenue
Tie-in new water main existing line

Reidville Drive
Excavate and install support of excavation at Culvert 003 (just east of the rock cut)
Excavation & trucking of materials
One lane closed intermittently with alternating traffic

Harpers Ferry Road/Brookdale Lane
Complete driveways and sidewalk

Plank Road
Install 18” water main east of Harpers Ferry Road

Scott Road (Culvert 014 at Scott Road south of WB 25 off ramp)
Install sewer under culvert

Rock Blasting
Rock blasting to occur along Reidville Drive. When I-84 needs to be stopped for safety reasons, blasting will occur on Tuesday, Wednesday, and Thursday between 9:30 AM and 11:30 AM. When no traffic stoppage on I-84 is required blasting may occur Monday through Friday from 9:00am – 3:00pm.Traffic stoppages on Harpers Ferry Road and Reidville Drive to be implemented at time of blasts for safety reasons.

Night Work
Lighting along I-84 median.

Waste Stockpile Area (WSA)/Reuse Stockpile Area (RSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to RSA at Exit 30 WB.