Construction Weekly Project Update 10/24/2016

Bridges

Bridge 4321 (Hamilton Avenue over I-84)

Bridge 1224 (I-84 over Mad River, western crossing)

Bridge 5774 (future I-84 over Mad River, eastern crossing)

Bridge 6284 (future EB 25 off ramp over Mad River)

Bridge 1226 (Harpers Ferry Road over I-84)

Bridge 1228 (Scott Road Bridge over I-84)

Retaining Walls

Retaining Wall 108 (along I-84, east of WB 25 on ramp)

Retaining Wall 113 and 114 (along both sides of future EB 25 off ramp)

I-84

Median reconstruction from Pierpont Road to WB 25 off ramp

I-84 EB (Between EB 23 on ramp and Bridge 1224)

EB 23 on ramp

I-84 EB from east of EB 23 off ramp

Local Roads

Hamilton Avenue

Reidville Drive

Harpers Ferry Road/Plank Road

Scott Road (Culvert 014 at Scott Road south of WB 25 off ramp)

Plank Road East (Culvert 02537 at Beaver Pond Brook under WB I-84 east of WB 25 on ramp)

Rock Blasting

Rock blasting to occur along Reidville Drive. When I-84 needs to be stopped for safety reasons, blasting will occur on Tuesday, Wednesday, and Thursday between 9:30 AM and 11:30 AM. When no traffic stoppage on I-84 is required blasting may occur Monday through Friday from 9:00am – 3:00pm. Traffic stoppages on Harpers Ferry Road and Reidville Drive to be implemented at time of blasts for safety reasons.

Night Work

Lane closure on I-84, 9:30 PM to 6:00 AM, Sunday through Thursday nights for barrier, grading and drainage work.