Construction Weekly Project Update 10/10/2016

Bridges

Bridge 4321 (Hamilton Avenue over I-84)

Bridge 1224 (I-84 over Mad River, western crossing)

Bridge 5774 (future I-84 over Mad River, eastern crossing)

Bridge 6284 (future EB 25 off ramp over Mad River)

Bridge 1226 (Harpers Ferry Road over I-84)

Bridge 1228 (Scott Road Bridge over I-84)

Retaining Walls

Retaining Wall 106 (north of WB I-84 west of WB 25 off ramp)

Retaining Wall 113 and 114 (along both sides of future EB 25 off ramp)

Retaining Wall 116 (along Harpers Ferry Road in vicinity of Bridge 5774 abutment 2)

I-84

Median reconstruction from Pierpont Road to WB 25 off ramp

I-84 EB (Between EB 23 on ramp and Bridge 1224)

EB 23 Off Ramp

Local Roads

Hamilton Avenue

Reidville Drive

Scott Road (Culvert 014 at Scott Road south of WB 25 off ramp)

Plank Road East (Culvert 02537 Beaver Pond Brook under WB I-84 east of WB 25 on ramp)

Pipe Work

Reidville Drive

Harpers Ferry Road/Plank Road

Rock Blasting

Rock blasting to occur along Reidville Drive. When I-84 needs to be stopped for safety reasons, blasting will occur on Tuesday, Wednesday, and Thursday between 9:30 AM and 11:30 AM. When no traffic stoppage on I-84 is required blasting may occur Monday through Friday from 9:00am – 3:00pm. Traffic stoppages on Harpers Ferry Road and Reidville Drive to be implemented at time of blasts for safety reasons.

Night Work

Lane closure on I-84, 9:30 PM to 6:00 AM, Sunday through Thursday nights for barrier, grading and drainage work.

Waste Stockpile Area (WSA)/Reuse Stockpile Area (RSA)