Construction Weekly Project Update 10/03/2016
- Bridges
- Retaining Walls
- I-84
- Local Roads
- Pipe Work
- Rock Blasting
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Install approach slabs abutment 1 & 2
- Form and rebar parapet and sidewalk
- Complete 14” water main installation north of bridge
Bridge 1224 (I-84 over Mad River, western crossing)
- Demolition of northern portion of bridge
Bridge 5774 (future I-84 over Mad River, eastern crossing)
Bridge 6284 (future EB 25 off ramp over Mad River)
- Steel delivery/set structural steel
- Form and pour backwalls abutment 2
Bridge 1226 (Harpers Ferry Road over I-84)
Bridge 1228 (Scott Road Bridge over I-84)
- Pour abutment 2 footing (north of I-84)
- Excavate for footing at abutment 1 (south side of I-84)
Retaining Walls
Retaining Wall 106 (north of WB I-84 west of WB 25 off ramp)
- Regrade slope for soil samples
Retaining Wall 113 and 114 (along both sides of future EB 25 off ramp)
- Install parapet moment slab 113
I-84
EB 23 Off Ramp
Local Roads
Reidville Drive
- Excavate and install support of excavation at Culvert 003 (just east of the rock cut)
- Excavation & trucking of materials
- One lane closed intermittently with alternating traffic
East Main Street
- Drainage and utility work in commuter lot vicinity (east of Scott Road)
Scott Road (Culvert 014 at Scott Road south of WB 25 off ramp)
- Excavate and install temporary earth retaining system
- Install utilities
Plank Road East
- Form and pour moment slabs (west of Scott Road Culvert 06622)
- Excavate and install support of excavation at Culvert 02537 (Beaver Pond Brook WB I-84 east of WB 25 on ramp)
- Form and pour Culvert 02537 footing
Pipe Work
Hamilton Avenue
Harpers Ferry Road/Plank Road
- Install water main and services
Scott Rd/East Main Street
- Install permanent and temporary drainage
Rock Blasting
Rock blasting to occur along Reidville Drive. When I-84 needs to be stopped for safety reasons, blasting will occur on Tuesday, Wednesday, and Thursday between 9:30 AM and 11:30 AM. When no traffic stoppage on I-84 is required blasting may occur Monday through Friday from 9:00am – 3:00pm. Traffic stoppages on Harpers Ferry Road and Reidville Drive to be implemented at time of blasts for safety reasons.
Night Work
Lane closure on I-84, 9:30 PM to 6:00 AM, Sunday through Thursday nights for barrier, grading and drainage work.
Waste Stockpile Area (WSA)/Reuse Stockpile Area (RSA)
- Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing).
- Trucking excavated material to RSA at Exit 30 WB