Construction Weekly Project Update 9/26/2016
- Bridges
- Retaining Walls
- I-84
- Local Roads
- Pipe Work
- Rock Blasting
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Place concrete deck
- Form and rebar parapet and sidewalk
- Complete 14” water main installation north of bridge
Bridge 1224 (I-84 over Mad River, western crossing)
- Install parapet EB 25 off ramp
- Demolition of northern portion of bridge
- Continue WB 25 off ramp deck work
Bridge 5774 (future I-84 over Mad River, eastern crossing)
Bridge 6284 (future EB 25 off ramp over Mad River)
- Steel delivery
- Form and pour backwalls abutment 2
Bridge 1226 (Harpers Ferry Road over I-84)
Bridge 1228 (Scott Road Bridge over I-84)
- Excavate for temporary earth retaining system abutment 1 (south of I-84)
- Pour abutment 2 footing (north of I-84)
Retaining Walls
Retaining Wall 106 (north of WB I-84 west of WB 25 off ramp)
Retaining Wall 113 and 114 (along both sides of future EB 25 off ramp)
- Install parapet moment slab
I-84
Median Reconstruction from Pierpont Road to WB 25 Off Ramp
- Excavate/grade/prepare for paving
EB 23 Off Ramp
- Full depth roadway excavation
EB I-84 (East of 23 on ramp)
- Drill foundation for noise wall
Local Roads
Plank Road/Harpers Ferry Road
- Gas work at Plank Road/Harpers Ferry Road intersection
Reidville Drive
- Excavate and install support of excavation at Culvert 003 (just east of the rock cut)
- Excavation & trucking of materials
- One lane closed intermittently with alternating traffic
Plank Road East (west of Scott Road Culvert 06622)
- Set wing wall blocks
- Form and pour moment slabs
Scott Road (Culvert 014 at Scott Road south of WB 25 off ramp)
- Excavate and install temporary earth retaining system
Pipe Work
Scott Rd/East Main Street
- Install permanent and temporary drainage
Reidville Drive
- Install sewer at receiving pit east of rock cut
Rock Blasting
Rock blasting to occur along Reidville Drive. When I-84 needs to be stopped for safety reasons, blasting will occur on Tuesday, Wednesday, and Thursday between 9:30 AM and 11:30 AM. When no traffic stoppage on I-84 is required blasting may occur Monday through Friday from 9:00am – 3:00pm.Traffic stoppages on Harpers Ferry Road and Reidville Drive to be implemented at time of blasts for safety reasons.
Night Work
Lane closure on I-84, 9:30 PM to 6:00 AM, Sunday through Thursday nights for barrier, grading, drainage work, and traffic shift WB I-84 Bridge 1224.
Waste Stockpile Area (WSA)/Reuse Stockpile Area (RSA)
- Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing).
- Trucking excavated material to RSA at Exit 30 WB