Construction Weekly Project Update 9/19/2016
- Bridges
- Retaining Walls
- I-84
- Local Roads
- Pipe Work
- Rock Blasting
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Install Gomaco deck machine dry run
- Place concrete deck
Bridge 1224 (I-84 over Mad River, western crossing)
- Install parapet EB 25 off ramp
- Mobilize for demolition of northern portion of bridge
Bridge 5774 (future I-84 over Mad River, eastern crossing)
- Backfill footing abutment 2
Bridge 6284 (future EB 25 off ramp over Mad River)
- Form and pour backwalls abutment 2
Bridge 1226 (Harpers Ferry Road over I-84)
- Form and pour abutment 1 stem
Bridge 1228 (Scott Road Bridge over I-84)
- Excavate for temporary earth retaining system abutment 1 (south of I-84)
- Form and pour abutment 2 footing (north of I-84)
Retaining Walls
Retaining Wall 106 (north of WB I-84 west of WB 25 off ramp)
Retaining Wall 108 (along I-84, east of WB 25 on ramp)
Retaining Wall 113 and 114 (along both sides of future EB 25 off ramp)
- Install parapet moment slab
I-84
Median Reconstruction from Pierpont Road to WB 25 Off Ramp
Local Roads
Plank Road
- Gas work at Plank Road/Harpers Ferry Road intersection
Reidville Drive
- Excavate and install support of excavation
- One lane closed intermittently with alternating traffic
- Excavation and trucking of materials
Plank Road East (west of Scott Road Culvert 06622)
Scott Road (Culvert 014 at Scott Road south of WB 25 off ramp)
- Mobilize for traffic shift
- Install temporary signalization
- Shift both lanes of traffic on Scott Road, north of Scott Road Bridge, to the east over the new culvert, south of East Main Street
Pipe Work
Scott Rd/East Main Street
- Install permanent and temporary drainage
Hamilton Avenue/Plank Road
Rock Blasting
No rock blasting is anticipated this week; Rock blasting will resume at a future date.
Night Work
Lane closure on I-84, 9:30 PM to 6:00 AM, Sunday through Thursday nights for barrier, grading, drainage work, and traffic shift WB I-84 Bridge 1224.
Waste Stockpile Area (WSA)/Reuse Stockpile Area (RSA)
- Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing).
- Trucking excavated material to RSA at Exit 30 WB