Construction Weekly Project Update 8/29/2016
- Bridges
- Retaining Walls
- I-84
- Preload Area
- Local Roads
- Rock Blasting
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Feed water main through sleeve
- Form and prep deck
Bridge 1224 (I-84 over Mad River, western crossing)
- Install parapet EB 25 off ramp
- Waterproof mainline deck
Bridge 5774 (future I-84 over Mad River, eastern crossing)
- Rebar, form and pour footing abutment 2
Bridge 6284 (future EB 25 off ramp over Mad River)
- Rebar, form and pour wing walls
- Prep for steel delivery
Bridge 1226 (Harpers Ferry Road over I-84)
- Form and pour abutment 1 stem
Bridge 1228 (Scott Road Bridge over I-84)
- Excavate for temporary earth retaining system abutment 1
Retaining Walls
Retaining Wall 108 (along I-84, east of WB 25 on ramp)
- Form and pour leveling pad
Retaining Wall 113 and 114 (along both sides of future EB 25 off ramp)
- Continue to install concrete cap
- Set parapet Wall 114
I-84
Traffic Stoppages west of Hamilton Ave Sunday night August 28 from 11:00 PM to 5:00 AM
- Traffic to be stopped intermittently for safety reasons for overhead utility line installation/removal
I-84 EB 23 off ramp (temporary EB Exit 23 off ramp Hamilton Ave)
- Cut and fill to subgrade
- Place processed aggregate
Median reconstruction from Pierpont Road to WB 25 off ramp
- Full depth roadway excavation
I-84 Exit WB 25 off ramp (Beaver Pond Brook/Scott Road)
Excavation/rock removal
I-84 EB 23 off ramp (vicinity of Retaining Wall 112 Hamilton Avenue)
- Prep work and install noise barrier wall
Preload Area (South of I-84 between Mad River crossings)
- Pave in vicinity of Bridge 1224
Local Roads
Reidville Drive
- Backfill and pave temporary roadway at Culvert 003 (just east of the rock cut)
- Shift traffic at Culvert 003 over the newly paved southern half of the culvert (so the northern half can be constructed)
- One lane closed intermittently with alternating traffic
- Excavation and trucking of materials
Plank Road East (west of Scott Road Culvert 06622)
Scott Road (Culvert 014 at Scott Road south of WB 25 off ramp)
- Backfill Gabions Earth Retaining System
- Install drainage and full-depth roadway
Rock Blasting
No rock blasting is anticipated this week; Rock blasting will resume at a future date.
Night Work
Lane closure on I-84, 9:30 PM to 6:00 AM, Sunday through Thursday nights for barrier, grading, and drainage work.
Waste Stockpile Area (WSA)/Reuse Stockpile Area (RSA)
- Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing).
- Trucking excavated material to RSA at Exit 30 WB