Construction Weekly Project Update 8/22/2016
- Bridges
- Retaining Walls
- I-84
- Preload Area
- Local Roads
- Rock Blasting
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Install water main
- Form and prep deck
- Install Gomaco Deck Machine for dry run
Bridge 1224 (I-84 over Mad River, western crossing)
Bridge 5774 (future I-84 over Mad River, eastern crossing)
- Rebar, form and pour abutment 2
- Place granular fill abutment 2
Bridge 6284 (future EB 25 off ramp over Mad River)
- Rebar, form and pour wing walls
Bridge 1226 (Harpers Ferry Road over I-84)
- Form and pour abutment 1 stem
Bridge 1228 (Scott Road Bridge over I-84)
- Excavate for temporary earth retaining system abutments 1 & 2
Retaining Walls
Retaining Wall 108 (along I-84, east of WB 25 on ramp)
Retaining Wall 109 (along I-84, east of WB Exit 25 off ramp)
- Set parapet
- Install moment slab
Retaining Wall 113 and 114 (along both sides of future EB 25 off ramp)
- Continue to install concrete cap
I-84
I-84 EB 23 off ramp (EB Exit 23 Hamilton Ave.)
- Continue to install panels for noise barrier wall
Median reconstruction WB Hamilton Avenue to Washington Street
- Pave remaining 200’ median section toward Hamilton Avenue pier
I-84 WB (From Retaining Wall 111 at Pierpont Rd west to Exit 25 WB off ramp)
- Place subbase and pave
- Traffic shift: Beginning Wednesday night, August 24, both lanes of I-84 westbound traffic will be shifted to the north, adjacent to its current path, west of Pierpont Road to the vicinity of Exit 25. This temporary shift is for construction work in the median between Pierpont Road and the WB Exit 25 off ramp.
Preload Area (South of I-84 between Mad River crossings)
- Establish subbase and prepare for paving
Local Roads
Reidville Drive
- One lane closed intermittently with alternating traffic
- Excavation and trucking of materials
Plank Road East (west of Scott Road Culvert 06622)
- Form and pour wing wall leveling pad
Scott Road (Culvert 014 at Scott Road south of WB 25 off ramp)
- Backfill Gabions Earth Retaining System
- Install drainage and full-depth roadway
Rock Blasting
No rock blasting is anticipated this week; Rock blasting will resume at a future date.
Night Work
Lane closure on I-84, 9:30 PM to 6:00 AM, Sunday through Thursday nights for barrier, grading, and drainage work.
Waste Stockpile Area (WSA)/Reuse Stockpile Area (RSA)
- Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing).
- Trucking excavated material to RSA at Exit 30 WB