Construction Weekly Project Update 8/15/2016
- Bridges
- Retaining Walls
- I-84
- Local Roads
- Rock Blasting
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Install water main
- Pull cable and splice
Bridge 1224 (I-84 over Mad River, western crossing)
- Install approach slabs
- Install mainline parapet
Bridge 5774 (future I-84 over Mad River, eastern crossing)
- Drive production piles abutment 2
- Place granular fill abutment 2
Bridge 6284 (future EB 25 off ramp over Mad River)
- Rebar, form and pour wing walls
- Form and pour pedestals abutment 2
Bridge 1226 (Harpers Ferry Road over I-84)
- Form and pour abutment 1 stem
Bridge 1228 (Scott Road Bridge over I-84)
- Excavate for temporary earth retaining system abutment 2
- Form and pour abutment 2 footing
Retaining Walls
Retaining Wall 101 (along I-84, east of WB Exit 23 off ramp)
- Set final parapet section and moment slab
Retaining Wall 108 (along I-84, east of WB 25 on ramp)
- Excavate and install temporary earth retaining system
Retaining Wall 109 (along I-84, east of WB Exit 25 off ramp)
- Set parapet
- Install moment slab
Retaining Wall 113 and 114 (along both sides of future EB 25 off ramp)
- Continue to install concrete cap
- Set parapet 113
I-84
I-84 EB 23 off ramp (EB Exit 23 Hamilton Ave.)
- Continue to install panels for noise barrier wall
I-84 WB 25 off ramp (Beaver Pond Brook/Scott Road)
I-84 WB (From Retaining Wall 111 at Pierpont Rd west to Retaining Wall 109)
- Place subbase and prepare for paving
Local Roads
Reidville Drive
- Backfill and pave temporary roadway at Culvert 003 (just east of the rock cut)
- One lane closed intermittently with alternating traffic
- Excavation and trucking of materials
Harpers Ferry Road
- Install permanent drainage
Plank Road East (west of Scott Road Culvert 06622)
- Form and pour wing wall leveling pad
Scott Road (Culvert 014 at Scott Road south of WB 25 off ramp)
- Backfill Gabions Earth Retaining System
Rock Blasting
No rock blasting is anticipated this week; Rock blasting will resume at a future date.
Night Work
Lane closure on I-84, 9:30 PM to 6:00 AM, Sunday through Thursday nights for barrier, grading, and drainage work.
Waste Stockpile Area (WSA)/Reuse Stockpile Area (RSA)
- Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing).
- Trucking excavated material to RSA at Exit 30 WB