Construction Weekly Project Update 8/01/2016
- Bridges
- Retaining Walls
- I-84
- Sewer Work
- Local Roads
- Rock Blasting
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Install stay in place forms for bridge deck
- Pull cable and splice
Bridge 1224 (I-84 over Mad River, western crossing)
- Install mainline parapet
- Install electrical conduit
Bridge 5774 (future I-84 over Mad River, eastern crossing)
- Drive production piles abutment 2
Bridge 6284 (future EB 25 off ramp over Mad River)
- Rebar, form, and pour stemwalls abutment 2
Bridge 1226 (Harpers Ferry Road over I-84)
- Form and pour pier stem
- Form and pour abutment 1 stem
Bridge 1228 (Scott Road Bridge over I-84)
- Excavate for temporary earth retaining system abutment 2
Retaining Walls
Retaining Wall 101 (along I-84, east of WB Exit 23 off ramp)
- Install remaining retaining wall and moment slab
Retaining Wall 108 (along I-84, east of WB 25 on ramp)
- Excavate and install temporary earth retaining system
Retaining Wall 109 (along I-84, east of WB Exit 25 off ramp)
Retaining Wall 113 and 114 (along both sides of future EB 25 off ramp)
I-84
I-84 WB 23 off ramp (east of Hamilton Avenue)
- Establish subgrade behind Retaining Wall 101
Median reconstruction WB Hamilton Avenue to Washington Street
- Form and pour barrier transition
- Install median cap
I-84 EB 23 off ramp (EB Exit 23 Hamilton Ave)
- Continue to install panels for noise barrier wall
I-84 EB 25 on ramp (from Scott Road)
- Install ramp lighting and conduit
Sewer Work
Retaining Wall 104 (south of EB 23 on ramp)
- Install remaining sewer behind wall
I-84 WB 25 off ramp (Beaver Pond Brook/Scott Road)
Local Roads
Reidville Drive
- Backfill and pave temporary roadway at Culvert 003 (just east of the rock cut)
- One lane closed intermittently with alternating traffic
- Excavation and trucking of materials
Plank Road East (west of Scott Road Culvert 06622)
- Form and pour wing wall leveling pad
Scott Road (Culvert 014 at Scott Road south of WB 25 off ramp)
- Form and pour wing wall leveling pad
- Set wing wall blocks
Rock Blasting
- Rock blasting to occur along Reidville Drive and along WB 25 off ramp.
When I-84 needs to be stopped for safety reasons, blasting will occur on Tuesday, Wednesday and Thursday between 9:30 AM and 11:30 AM. When no traffic stoppage on I-84 is required blasting may occur Monday through Friday from 9:00 AM – 3:00 PM.
- Traffic stoppages on Hamilton Ave., Harpers Ferry Road, Scott Road and Reidville Drive to be implemented at time of blasts for safety reasons.
Night Work
Lane closure on I-84, 9:30 PM to 6:00 AM, Sunday through Thursday nights for barrier, grading, and drainage work.
Waste Stockpile Area (WSA)/Reuse Stockpile Area (RSA)
- Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing).
- Trucking excavated material to RSA at Exit 30 WB