Construction Weekly Project Update 7/18/2016
- Bridges
- Retaining Walls
- I-84
- Sewer Work
- Local Roads
- Rock Blasting
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Install Stay in place forms
- Install communication conduit
Bridge 1224 (I-84 over Mad River, western crossing)
- Begin to place concrete deck, mainline
Bridge 5774 (future I-84 over Mad River, eastern crossing)
- Drive production piles abutment 2
Bridge 6284 (future EB 25 off ramp over Mad River)
- Rebar, form, and pour stemwalls abutment 2
Bridge 1226 (Harpers Ferry Road over I-84)
- Form and pour pier stem
- Form and pour abutment 1 stem
Bridge 1228 (Scott Road Bridge over I-84)
- Excavate for temporary earth retaining system abutment 2
Retaining Walls
Retaining Wall 101 (along I-84 east, of WB Exit 23 off ramp)
- Continue to set blocks and backfill
- Set moment slab
Retaining Wall 108 (along I-84, east of WB 25 on ramp)
- Excavate and install temporary earth retaining system
Retaining Wall 113 and 114 (along both sides of future EB 25 off ramp)
I-84
Median reconstruction WB Hamilton Avenue to Washington Street
- Install permanent barrier and electrical conduits
I-84 EB 23 on ramp (in front of Retaining Wall 104)
- Install barrier
- Install electrical conduit
I-84 EB 23 off ramp (EB Exit 23 Hamilton Ave)
- Prep work and install panels for noise barrier wall
Sewer Work
Jacking Pit (under I-84 adjacent to former WB 24 off ramp)
- Install chamber and tie-in sewer
I-84 WB 25 off ramp (Beaver Pond Brook/Scott Road)
Local Roads
Reidville Drive
- Gas work at Culvert 003 (just east of the rock cut)
- One lane closed intermittently with alternating traffic
- Excavation and trucking of materials
Scott Road (Culvert 014 at Scott Road south of WB 25 off ramp)
- Install gabions earth retaining system
Rock Blasting
- Rock blasting to occur along Reidville Drive. When I-84 needs to be stopped for safety reasons, blasting will occur on Tuesday, Wednesday and Thursday between 9:30AM and 11:30AM. When no traffic stoppage on I-84 is required blasting may occur Monday through Friday from 9:00AM – 3:00PM.
- Traffic stoppages on Hamilton Ave., Harpers Ferry Road and Reidville Drive to be implemented at time of blasts for safety reasons.
Waste Stockpile Area (WSA)/Reuse Stockpile Area (RSA)
- Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing).
- Trucking excavated material to RSA at Exit 30 WB
Night Work
Night work is anticipated to continue on I-84 within the project limits (I-84 between Washington Street and Pierpont Road) when it is necessary to close a lane on I-84 for safety purposes from 9:30 PM to 6:00 AM, Sunday through Thursday.